Cement deliveries are limited. Is it because of too high demand or a cartel? Construction costs keep growing. Cement importers thrive.

Concrete producers cannot meet the demand. Concrete sales jumped 50 percent against 2006 but it’s still not enough for construction companies. Cement producers delivering the material for concrete, limit deliveries. At first, there were monthly limits, now there are weekly ones.

“We received a letter from Gorazdze cement producer this week. The deliveries are already 35 percent lower than our demand”, Kazimierz Ladyzynski, Hydrobudowa 1 Betoniarnia-Laboratorium CEO.

This middle-sized plant produces 60,000 cubic meters of concrete annually. “Six months ago, Gorazdze representatives told us unofficially that the orders exceed their capacity by 1m tons. Our main deliverer will be able to meet the demand in 2-3 years”, Kazimierz Ladyzynski added.
 
Gorazdze representatives believe that every company submitting its order at the beginning of the year will receive all the cement but in certain periods.
“If the client buys 100,000 tons of cement, he will be able to buy maximum 25,000 tons in a week”, Andrzej Balcerek, Gorazdze CEO said.

Concrete producers are in trouble because they have contracts with construction companies signed for over 12 months. Concrete producers lose their clients. Construction companies have troubles because due to the lack of materials, they have to pay more for leasing construction equipment.

Concrete producers buys cement from importers and cement trading companies. “You have to pay them 20-25 percent more”, the head of Hydrobudowa1 LB said.
Cement producers calm down and assure that the present situation is caused by too many orders.

“This year, the sector will produce 17m tons of cement while its capacities amount to 18-19m tons annually. We will have 1m tons of reserves”, Andrzej Balcerek explained. “19m tons would be produced if the plants worked 12 months a year. But they produce seasonally plus spend one month for repairs”, Rudiger Kuhn, Cemex Polska CEO said. If his company has not enough cement, it imports it from Germany. These are not big quantities, however, because there is not enough cement in Germany as well.
 
In December 2006, the competition and consumer protection office UOKiK launched investigation against cement producers. The office suspects that there was a cartel made by them. Despite possible sanctions, the companies raised cement prices in April. UOKiK’s proceeding is still going on.