The average output of oil consists 41-42 % that corresponds planned targets.
At the factory have been completely replaced oil extractors, the heating equipment, product and oil pipelines, there were expanded storage reservoirs as well.
The Group informs that installation of 2nd line is coming to an end. Its technical start is planned for the end of February. By the end of winter the Group plans to finish the setup and configuration of the equipment and reach the amount of processing of 55 thousand tons of sunflower per year.
Re-equipment of the refining factory is financed from revenues from the issuance of shares under the private placement which took place in February 2011. Increase the capacity of processing is an essential part of strategic development of the Group.
“Legal basis: § 3.1 of the Exhibit 3 to the Alternative Trading System Rules “Current and Periodical Information in the Alternative Trading System on the NewConnect Market"
Osoby reprezentujące spółkę:
- Alexandr Berdnyk - Chairman of the Board of Directors